Phase I
Comprehensive Re-Roof and Drainage
Rehabilitation Program
New compatible roofing material,
underlayments and related
Tear-off-down to existing skip
sheathing
Select structural roof framing
repair/reinforcing
New flashing/sealants/crickets and
cants.
New prefabricated roof hatch &
curb
Temporary weather protection and
access/safety allowance
Re-roof with period shingles
Contingency @ 15%
Plans, specs and technical field
assistance @ 15%
Window & Door Restoration
Window, door and related millwork
restoration
Reproduce front doors/compatible
hardware allowance
Front fan light transom
restoration and related
Restore 32 type “A” double hung
windows
Restore 2 type “B” double hung
windows
Restore 6 type “C” double hung
windows
Window hardware and weather
stripping allowance
40 windows
New wood, compatible storm
security sash and related
millwork restoration allowance -
40 windows
Lead abatement/safety allowance
Contingency @ 10%
Plans, specs and technical field
assistance @ 10%
Fire Detection and
Security
Fire detection and security system
Intruder sensor/alarm system
allowance (2 floors)
Smoke and heat sensors/alarms
allowance
(2 floors + crawl + attic)
Monitor/annunciation
system/devices allowance
Miscellaneous related electrical
allowance
Related finishes repair allowance
Contingency @ 15%
Plans, specs and technical field
assistance @ 15%
|